Outputs

  • Kick off meeting in Brussels;  21.01.2013
  • Transnational coordination meetings + Financial coordination meetings:

>Tampere 11-12.3.13

> London M8  9-11. 10.13 (inclusive one day workshop with EU experts)
> Essen M12 end of February 2014
> Rovigo M20

  • On-line coodination meetings

> M3 10. April 2013 at 10 CET (skype coordinating Synergia)
> M9
> M15
> M18



Outcomes



  • 0.1. Minutes of the transnational meetings and on-line meetings
  • 0.2. Operative Work Plan – have delivered to participants
  • 0.3. Mid term financial report –M12
  • 0.4. Final financial report – M24
  • 0.5. On-going Monitoring report – on-going (Synergia)
  • 0.6. External evaluation report – M24
  • 0.7. Final activity report – M24

 